Wednesday, August 26, 2020
Moving Geek
Tuesday, August 25, 2020
Almost There!
Thursday, August 20, 2020
All Reviews Finished, but Still Not Done Yet
I asked for another update, since we can see the plans were approved on Monday. Seems like there's more steps to go, which just sound like nonsense to me.
The next step is it goes to Mr. D for quality control. She has no idea how long quality control is taking, especially since Mr. D was just promoted to the position. Then it goes to Ms. G for quality assurance. Wait...it just went through quality control, then it needs to go through quality assurance? You're kidding, right?
So, we're back to having no clue how long it will be until we get our permit. I'm getting impatient. Yesterday was 19 weeks since our permit was officially received.
Monday, August 17, 2020
A Little Bit Closer
The King County system shows the plan reviewer signed off on "Construction Services Review" today. But "Engineering Services Review still appears to be pending with no one assigned to review it yet. And our overall permit still shows "Reviews in Progress". I'm waiting to hear from our builder as far as what this means, but it does seem like we made some progress today.
Thursday, August 13, 2020
Finally A Permit Update
Our builder gave us the green light to email the plan reviewer and ask for a status update. We sent that last night and today he responded that he has two plans ahead of ours, but he expects to start our review tomorrow or Monday. Yay!
We've been told once plan review is over, it usually takes the permit tech about a week to collect all the documents and be ready to issue the permit. But our builder said he would reach out to the tech to see if it could be ready any faster.
With this update our builder can begin lining up subs for the initial steps of our build. It feels like we're close to the fun part!