7.21.2019 - Initial Visit to Property
7.23.2019 - Mutual Acceptance
7.29.2019 - Submit Critical Areas Designation Application to King County
9.12.2019 - Closed on Land (Happy Birthday Jeremy!)
9.19.2019 - Critical Areas Designation Approval (No Critical Areas Found)
10.21.2019 - Septic/Well Application Submitted to Public Health
11.07.2019 - 1st Meeting with Architect
11.21.2019 - 2nd Meeting with Architect
12.20.2019 - 1st Meeting with Builder
1.09.2020 - Hired Builder
1.16.2020 - 3rd Meeting with Architect
1.23.2020 - Walk Property with Builder
2.01.2020 - Receive Septic/Well Design Approval from Public Health (dated 1.16.20)
2.03.2020 - 4th Meeting with Architect (design almost complete)
2.10.2020 - 5th & Final Meeting with Architect. Floor plan finished
2.14.2020 - King County Approval to create road to well site
3.20.2020 - Driveway Clearing Begins
3.25.2020 - Well Drilling Begins
3.30.2020 - Well Drillers Hit Water
4.01.2020 - Drainage Engineering Complete
4.02.2020 - Receive Final Plans from Architect; Applied for Building Permit
9.08.2020 - Permit Issued!
10.05.2020 - Old Well Decommissioned
10.08.2020 - Clearing Begins
10.29.2020 - Excavation Begins
11.04.2020 - Foundation Begins
11.10.2020 - Footings Poured
11.24.2020 - Foundation Walls Poured
01.18.2021 - Lumber Delivery #1; Framing Begins
01.19.2021 - Power to Temporary Pole
01.27.2021 - Under Floor Inspection Passed
02.24.2021 - Truss Delivery
03.19.2021 - Framing Complete
03.23.2021 - Roofing Day 1
03.31.2021 - Roofing Complete
04.05.2021 - Garage Floor Poured
04.26.2021 - Plumbing Day One
05.03.2021 - Windows & Sliding Doors Installed
05.05.2021 - HVAC Day One
05.17.2021 - Siding Day One
05.18.2021 - Fire Sprinkler Day One
05.27.2021 - Electrical Day One
07.02.2021 - Permanent Electricity & Water
07.21.2021 - Insulation Begins
07.26.2021 - Drywall Begins
08.24.2021 - Interior Paint Begins
08.25.2021 - Garage Doors Installed
09.08.2021 - Tile Begins
09.13.2021 - Cabinet Install Begins
09.23.2021 - Countertop Templating
10.05.2021 - Countertops Installed
10.08.2021 - Hardwood Flooring Delivered
11.16.2021 - Interior Millwork & Window Paint Begins
03.15.2022 - Final Inspection Complete