Framing Week 6 Day 2

The end wall of Vivian's room went up today, and the front wall of her bathroom is in-progress.  
The brackets that attach to the rods going into the foundation are installed and there are many of them throughout the main floor.  
The two big beams for the back patio were set today.  I'm still in awe of their carpentry skills.  
Measurements were taken for our windows and patio doors, and we made final decisions about how they'll look and function.  Even though they couldn't have measured for windows even a day earlier, we'll still be waiting on them a bit because they're taking 8 weeks to deliver.  But it couldn't be helped, and they'll be worth the wait.

The peaked end wall of Viv's room is in place.
The front wall of Viv's bathroom is in-progress.
10X14 beams WAY up high.
10 lags each.  The house isn't going anywhere.
All the window openings are marked.  This is the center picture window in the kitchen.