Thursday, March 18, 2021

Framing Week 9 Day 4

More roof progress today.  When we left the peak where he's working was almost closed up.  That will leave the area where the primary bedroom roof ties into the living room roof for tomorrow.  Then it's ready for roofing next week!  

There's a new vent pipe in the roof out back. 
 
The extra bracing for the range hood is in too.  
Due to some changes we made to the fireplaces and partly due to a mixup in the estimate, we learned the stone mason estimate was WAY more than we'd planned.  In an efffort to rescue the budget we decided tonight to not put stone on the front two bumpouts as planned.  We think there are enough other interesting elements on the front of the house that it will still look nice.