Tuesday, June 22, 2021

Shower Valves

The plumbers were back today working on the plumbing rough-in.  We had an issue with hose bibs not fitting, but we found a way around the problem.  There's new shower valves and Maya's tub is in.  Looks like they have a bit more to do but they're close to wrapping things up.  


The electrician is still there tonight finishing off the last of the wiring.  They've requested the inspection for tomorrow.  

More dirt arrived.  We've said once they finish hauling in dirt this week let's call it good and work with whatever we've got.