We had about 5 minutes tonight to check out the primed and textured walls and the fireplace progress that happened while we were gone. It's still wet, but looks great.
This coming week while the interior walls are being painted, our cabinets will be built. They'll be delivered the following week, Aug 30-Sept 3.
Our move-in date is going to be a little later than we hoped. The most recent completion date is the 2nd week of January or sooner. We were hoping for a 2021 move for Jeremy's vacation accrual purposes, but it's not a big deal. We're happy the house is being built well and it'll be done when it's done.